Mealey Projects Ltd were asked by Heron Foods to undertake the project for the fit out of the new Store in Aspley, Nottingham.

​As the principle contractor for the fit out of the store we completed the following works to a supplied specification from Heron Foods.

  • ​A full rip out of the existing building.
  • Installation of Electrical Systems: Wiring for freezers, fridges, tills, sockets, fire alarms, bell system, plant, lights and Extraction.
  • Installation of new sub mains.
  • Installation of new plumbing.
  • Installation of new disabled WC.
  • Installation of new glazing at front of store
  • Installation of new partition walls.
  • Fit out of the stores staff room.
  • Construction and fit out for a new store office.
  • Installation of a new Kitchen.
  • Installation of a new low-level sink for cleaning.
  • Replace the floor with new floor tiles where needed, and new Polyfloor in the staff office.
  • Installation of air conditioning.
    Painting of the entire store area and back of house area.
  • Installation of new suspended ceiling, and repairs where needed
  • Full clearance of the service yard
  • Supply and install new gate to service yard.
  • Installation of all new freezers in the store.

All works were carried out to specification and the project was delivered on time for the Grand Opening of the store.

We continue to carry out works on multiple Heron Foods stores across the UK.